The battery power plant in Schwerin-Lankow was built in 2014 by Younicos AG in cooperation with WEMAG as client and owner.
It is the first battery power plant prequalified on the European primary control market.
The SCADA automation team supplied the control system for operational management based on zenon Energy Edition version 7.11.
A modern design in Full-HD resolution with an anthracite background is an eyecatcher and ensures a dazzle-free overview.
Especially when using the SLD view, conducting connections are capable for differentiation easily.
The SCADA system is concentrating incoming alarms to a few alarm classes and forwards to the super ordinated SCADA of the grid operator.
Graphical diagrams are supplementing scores of detail views of the plant, including functions for manual operation of the plant.